A boiler furnace pre-purge
a) is the shortest step in the start-up sequence
b) can take place normally even if there is a low water condition
c) must be done manually on a fully automatic boiler
d) must last a specific amount of time
e) will take place at the end of a boiler shutdown
Answer: D