A hydrostatic test on a high pressure steam boiler
a) must be done on a new boiler
b) must only be done by the inspector
c) will test the high pressure steam fuel cut-off
d) should be done with the Chief Engineer present
e) must be done before start-up of a boiler
Answer: A