Critical path planning is a:

Critical path planning is a:




a. Schedule drawn up to indicate the remaining operating hours of equipment
b. Method of scheduling maintenance work best suited for small plants
c. Method of scheduling maintenance outages for large plants
d. Method of determining plant output
e. Method of predicting the next equipment breakdown date.


Answer: C

Convenience assignment maintenance scheduling:

Convenience assignment maintenance scheduling:




a. Allows maintenance to be completed at the convenience of the production manager
b. Allows high pressure boiler inspections to be deferred to a three year schedule
c. Assigns maintenance work to be completed the next time the unit is out of operation for some other reason
d. Allows the maintenance staff to complete the maintenance at their convenience
e. Allows maintenance work to be completed on a semi-annual basis.



Answer: C