Gantt charts are used to plan:

Gantt charts are used to plan:



1. Shift schedules.
2. Large and long overalls.
3. Holiday schedule.
4. Day to day operation of the plant.



a. 1,3
b. 1,2
c. 2,3,4
d. 1,2,3
e. 1,2,3,4.



Answer: D