The pre-purge of a boiler furnace:
a. Is the shortest step in the start-up sequence
b. Can take place normally even if there is a low water condition
c. Must be done manually on a fully automatic boiler
d. Must last a specific amount of time
e. Will occur at the end of a boiler operating cycle
Answer: D